US 60 (Grand Avenue) and Bell Road weekly project update

ADOT Logo

The Arizona Department of Transportation (ADOT) has issued a project update for the Grand Avenue/Bell Road Interchange Project, which includes upcoming traffic restrictions and a schedule of on-site activities for the week of January 23.

Businesses in the Bell-Grand area are open during the construction project. View the latest Construction Business Access Map so you know how to ShopSurprise.

Familiarize yourself with the Bell Road Bridge and Grand Ave Traffic Patterns before the project is complete in spring 2017! View the ADOT Bell-Grand interchange animation*

The update is as follows:

Allow plenty of time and observe all traffic control signs and barricades. The project team appreciates your continued patience. If you have questions or concerns, please call the project hotline at (855) 712-8530 and press option #1, or send an email to bellandgrandinfo@azdot.gov.

View the weekly construction photos and additional information on the project website.  

Upcoming Activities

  • Grand Avenue base paving has been completed. Final paving will still need to be done and will require simultaneous closures of Towne Center Drive and Bell Grande. Final paving is anticipated to begin on Jan. 30.
  • Grand Avenue will be restricted to one lane in both directions at times over the next couple of weeks during daytime hours. Two lanes of traffic will be back in place at the end of each day.
  • Westbound Bell Road closed between 134th Avenue and West Point Parkway from 9 p.m. Saturday, Jan. 28, to 5 a.m. Monday, Jan. 30, for pavement work. DETOUR: Drivers can use Dysart Road to Grand Avenue and Litchfield Road to reconnect to westbound Bell Road.

**City, County, and State law enforcement will be patrolling the area. Please obey all traffic signage and posted speed limits. **

Project Overview

The Grand Avenue/Bell Road Interchange Project is using the design-build contracting method, which provides flexibility while the contractor’s designers work side-by-side with the construction team to deliver an improved connection between the two roadways. The project is scheduled to be completed in spring 2017.

The Grand Avenue/Bell Road Interchange project is part of the Maricopa Association of Governments’ Regional Transportation Plan approved by county voters in 2004. Funding sources include a county half-cent sales tax for transportation projects and the MAG region’s share of federal highway funds.

*Subject to change

Stay Informed – Keep In Touch  

For more information or if you have questions:

ADOT’s project hotline: (855) 712-8530, press option #1

Project email: bellandgrandinfo@azdot.gov

Project website: www.azdot.gov/bellandgrand  

Media inquiries: (800) 949-8057; email: news@azdot.gov


For more information about retail shopping and services in Surprise please see: Surprise Regional Chamber of Commerce: http://www.surpriseregionalchamber.com/


See press release...
Facebook Twitter Google Plus Email

Other News in City of Surprise News

Surprise Progress TV

New Surprise Progress TV Episode

Posted on: February 10, 2017
Surprise Progress TV

New Surprise Progress TV Episode

Posted on: January 20, 2017
health image

City hosts free Medicare workshops

Posted on: January 30, 2017
interview image

Career Success Workshop for Women

Posted on: January 27, 2017