Transportation Capital Improvement Projects

Significant projects in design review, recently approved, or under construction:

Greenway Road (Bullard Avenue to Litchfield Road):


This project includes half street improvements with a median. DMB is the project owner, with the City contributing to median costs. The project is expected to be completed in the spring of 2017. View Map

Projects completed in 2016:



Original Town Site (OTS) Infrastructure Improvement:


The project, which will begin in December and is scheduled to conclude February 2016, will replace old asphalt with pulverized asphalt in the OTS. Learn more

Waddell Road Median (Litchfield Road to 1200 feet west):


Work to add a landscaped median west of Litchfield Road began in January 2016 and is expected to run through February 2016. View Map

Landscaping Median (various locations):


The project focuses on completing medians in the following locations:
  • Reems Road—Peoria to Cactus (1 mile) ~$300K
  • Bullard Avenue—Peoria to Cholla (1/2 mile) ~$175K
  • Waddell Road—175th to Citrus (1/2 mile) ~$200
  • Sarival Road—Bell to Northwest Ranch Parkway (900 ft) ~$75K
Construction is expected to begin in the March/April 2016 timeframe with the individual sections prioritized as listed above. View Locations Map

Cactus Road (south side) from Litchfield Road to Rail Road Tracks and Litchfield Road (east side) from Cactus Road to Desert Cove Road:


The project will provide two travel lanes in one direction along Cactus (eastbound) and Litchfield (northbound). Construction is expected to begin in February 2016. View Map

Peoria Avenue (Reems Road to Sarival Avenue):


Project will provide two travel lanes in the westbound direction. Lennar has started construction, which is expected to be completed in February 2016. View Map

Peoria Avenue (south side) from Greer Ranch Parkway to Reems Road:


Construction will Project will provide two travel lanes in the eastbound direction. Construction will begin in April. View Map

Cactus Road (north half) from 143rd Avenue to Bullard Avenue:


This project includes half street improvements with a median. DMB is the project owner, with the City contributing to median costs. The project is expected to be completed in the spring of 2016. View Map

Greenway and Dysart Intersection:


Project will add an additional lane in each direction. This project began in January 2016. Work is scheduled to be completed in June 2016, weather permitting. View Map